Thursday, June 20, 2013

Pipeline almost done

The 62-mile pipeline from the Hickory Aquifer is 99.8 percent complete and will be finished by the end of July. That's what San Angelo Water Utilities Director Ricky Dickson told the city council. The remaining work on the 30-inch water main, which cost 39 million dollars to build, is occurring at the Concho River and at the water treatment plant. Dickson says that the line is gradually being filled so testing can begin next week.